Two tasks are running late. Both are three days behind schedule. One will delay the entire project, while the other won’t affect the delivery date at all.
Which one should you address first?
The answer depends on how those tasks connect to the rest of the project.
A deadline tells you when something should happen. A dependency tells you what needs to happen before it can. Understanding the difference is essential when planning projects, allocating resources and making delivery commitments.
Yet dependencies aren’t always obvious. They can exist between departments, within approval processes, across client projects or even in the availability of a single employee.
This guide explores the different types of project dependencies, how to identify them, and how to build a project schedule that can accommodate changes without losing sight of the delivery date.
What are project dependencies?
Project dependencies are relationships between tasks, resources, decisions or deliverables that influence when an activity can begin, progress or finish.
For example, a software testing team needs a completed application build before performing final acceptance testing. The availability of that build determines when testing can begin.
The activity providing the required input is known as the predecessor. The activity that relies on it is called the successor.
A simple dependency might look like this:
Requirements approval → Development → Testing → Deployment
However, most projects involve several interconnected activities. Some must follow a strict sequence, while others can progress simultaneously. Certain activities also depend on people or organisations outside the project team.
Dependency management involves identifying, documenting, monitoring and adjusting these relationships throughout the project lifecycle.
What are the four types of dependencies in project management?
There are four standard scheduling relationships used to define how activities influence one another. Choosing the correct relationship helps establish realistic start and finish dates without introducing unnecessary restrictions.
1. Finish-to-start (FS)
A finish-to-start dependency means the successor cannot begin until the predecessor finishes.
It is the most common scheduling relationship and applies when one activity must produce a completed output before another can proceed.
Example: A finance team cannot process a milestone-based invoice until the client accepts the completed deliverable.
The invoice depends on the acceptance of that deliverable. Scheduling both activities independently would overlook an essential business requirement.
2. Start-to-start (SS)
A start-to-start dependency means the successor cannot begin until the predecessor starts.
Unlike a finish-to-start relationship, it allows activities to overlap. They do not necessarily need to begin at exactly the same time.
Example: Once a system migration begins, the technical team can start monitoring data transfers and identifying errors.
There is no reason to wait until the entire migration finishes before monitoring it.
3. Finish-to-finish (FF)
A finish-to-finish dependency means the successor cannot finish until the predecessor finishes.
This relationship allows related activities to progress independently while ensuring their completion follows the required order.
Example: A technical writer can prepare product documentation during software development. However, the documentation cannot be finalised until the development team confirms the completed functionality.
4. Start-to-finish (SF)
A start-to-finish dependency means the successor cannot finish until the predecessor starts.
Although less common in project schedules, this relationship is useful in operational transitions, service continuity and shift handovers.
Example: An outgoing IT support team’s shift cannot end until the incoming team’s shift begins.
This ensures continuous support coverage during the transition.

Comparing the four dependency relationships
| Dependency type | Scheduling condition | Common application |
|---|---|---|
| Finish-to-start (FS) | Task B cannot start until Task A finishes | Approvals and sequential delivery |
| Start-to-start (SS) | Task B cannot start until Task A starts | Parallel activities |
| Finish-to-finish (FF) | Task B cannot finish until Task A finishes | Documentation and coordinated completion |
| Start-to-finish (SF) | Task B cannot finish until Task A starts | Service transitions and handovers |
These are standard relationships used in project scheduling.
Knowing which relationship to use matters because an incorrect dependency can make a project appear longer or more restrictive than it needs to be.
Why do project dependencies exist?
The four scheduling relationships explain how tasks connect. They don’t necessarily explain why the relationship exists.
For that, project managers need to consider the conditions behind each dependency.
Mandatory dependencies
Some activities must follow a specific sequence because of technical, physical, legal or contractual requirements.
For example, an organisation may need regulatory approval before introducing a regulated service.
Changing the project schedule cannot remove that requirement. The team must plan around it.
Discretionary dependencies
Other relationships exist because of a preferred working method.
A marketing team might choose to finish all campaign copy before starting visual design. While this approach may suit its existing process, preliminary layouts and visual concepts could potentially be developed earlier.
Discretionary dependencies are particularly useful to examine when a project needs to recover lost time.
Resource dependencies
Resource dependencies arise when activities compete for limited people, equipment or facilities.
Consider a consultancy delivering three client projects that all require the same solution architect. Each project might have a perfectly reasonable schedule when viewed independently.
The problem only becomes visible when those schedules are compared against the architect’s availability.
Resolving the conflict may require adjusted dates, alternative resources or a change in delivery priorities.
Internal and external dependencies
Internal dependencies involve work within the project’s boundaries, such as a development team delivering a feature for testing.
External dependencies originate outside those boundaries. They may involve customer decisions, supplier deliveries, another project or a third-party service provider.
An external dependency can exist even within the same organisation. A project waiting for another department’s approval may have limited control over when that approval arrives.
Dependencies can belong to several categories at once. A mandatory regulatory approval, for example, is also an external dependency.
Project dependencies vs constraints, blockers and risks
These terms are sometimes used interchangeably during project discussions, but they describe different situations.
| Term | What it describes | Example |
|---|---|---|
| Dependency | A relationship between activities or required inputs | Testing requires a completed build |
| Constraint | A restriction within which work must be delivered | The release must occur within an approved maintenance window |
| Blocker | An existing obstacle preventing work from progressing | The testing environment is unavailable |
| Risk | An uncertain event that could affect the project | The environment may not be ready when testing begins |
A dependency is not inherently a problem. Projects naturally contain many of them.
Problems arise when a required condition remains unmet at the point when another activity needs it.
Recognising this distinction helps teams avoid treating every planned dependency as an urgent issue.
How project dependencies affect deadlines and the critical path
A delay doesn’t necessarily mean a project will finish late. Its effect depends on where it occurs in the schedule.
Consider an illustrative website development project with the following activities:
| ID | Activity | Duration | Predecessor | Planned schedule |
|---|---|---|---|---|
| A | Prepare project brief | 2 days | None | Days 1–2 |
| B | Design website pages | 3 days | A | Days 3–5 |
| C | Write website content | 2 days | A | Days 3–4 |
| D | Approve website design | 1 day | B | Day 6 |
| E | Approve website content | 1 day | C | Day 5 |
| F | Develop website pages | 4 days | D | Days 7–10 |
| G | Integrate content and test | 2 days | E, F | Days 11–12 |
| H | Launch website | 1 day | G | Day 13 |

The project contains two main sequences of work.
Design and development: A → B → D → F → G → H
Content production: A → C → E → G → H
The first sequence takes 13 working days. The second takes eight. Assuming finish-to-start relationships, consistent working calendars and no additional resource restrictions, the first sequence determines the earliest project completion date.
This is the critical path.
What happens if design approval is delayed?
Suppose the client approves the design on Day 8 instead of Day 6.
Development now begins on Day 9. Integration and testing move to Days 13 and 14, and the website launches on Day 15.
Without a change to the remaining schedule, the two-day approval delay becomes a two-day project delay.
What happens if content approval is delayed?
Suppose content approval moves from Day 5 to Day 8 instead.
Integration is not scheduled to begin until Day 11. The content can arrive three days late without changing the planned launch date.
In this example, the content sequence has five working days of total float.
Float, sometimes called slack, is the amount of time an activity can be delayed without affecting the planned project completion date, subject to the schedule’s other conditions.
This is why two equally overdue tasks can require very different responses.
The project manager should prioritise the delay that threatens delivery while continuing to monitor the remaining activities. As the project changes, its critical path may change too.

How to identify project dependencies
Dependencies are easier to manage when they are discovered before the schedule is finalised. A useful starting point is to examine the inputs and outputs of each activity rather than simply arranging tasks by their preferred dates.
Start with deliverables instead of deadlines
Identify what each phase of the project needs to produce.
For a customer onboarding project, the deliverables might include a signed agreement, configured software, migrated data, trained users and an accepted implementation.
Work backwards from each deliverable to identify the activities and decisions required to produce it.
This approach makes it easier to discover missing steps before assigning dates to them.
Speak to the people performing the work
Project managers may understand the overall delivery process without knowing every technical requirement.
A developer might need API credentials that haven’t been requested. A consultant might require a specific dataset. A designer might need confirmation of product specifications.
Ask the person responsible for each activity what they need, who provides it and whether any part of their work can proceed independently.
These conversations frequently reveal dependencies that weren’t included in the initial project brief.
Look beyond production tasks
Approvals, access permissions, purchasing decisions and stakeholder availability are easy to underestimate because they may require little actual working time.
A client might need only 20 minutes to review a document, but obtaining that review could take several days.
Record important decisions and approvals as separate tasks or milestones. Assign responsibility for obtaining them and establish when they are required.
Check shared resources across projects
A dependency review should extend beyond the boundaries of an individual project when people work across multiple initiatives.
Two project managers may schedule activities for the same specialist without realising that their delivery commitments overlap.
Reviewing the wider resource schedule exposes these conflicts before they turn into missed handovers.
How to manage project dependencies effectively
Identifying dependencies is the planning exercise. Managing them is the ongoing work of keeping those relationships accurate as circumstances change.
1. Create a dependency map
A dependency map represents how activities connect, making it easier to understand their sequence and identify work that can proceed simultaneously.
Start by listing activities, recording their predecessors and identifying the appropriate relationship for each.
Depending on the project, you can represent these connections using a network diagram, Gantt chart, timeline or task relationship view.
A visual map is especially useful during planning meetings because team members can challenge assumptions about what must happen before something else begins.

2. Remove unnecessary scheduling restrictions
Imagine a project manager schedules every activity in a finish-to-start relationship because it feels easier to organise.
Research must finish before planning. Planning must finish before design. All design must finish before development.
The resulting schedule may be easy to read but unnecessarily long.
In reality, some research findings may be available early enough to begin preliminary planning. Approved sections of a design may also be ready for development before the entire design phase finishes.
Review each dependency and ask whether the complete preceding activity is genuinely required or whether an earlier, clearly defined deliverable would be sufficient.
Breaking large activities into smaller outputs can create scheduling flexibility without compromising quality.
3. Account for lead and lag time
A dependency may need an adjustment to reflect how work actually happens.
Lead allows a successor activity to begin earlier relative to its normal dependency relationship. Lag introduces a waiting period.
For instance, a team might begin preparing training materials before software development finishes. Alternatively, it might need to wait 24 hours after a system migration before completing a scheduled verification process.
These adjustments should reflect real working conditions, rather than being added simply to achieve a preferred deadline.
Read more about lead time and lag time in project management.
4. Assign responsibility for resolving dependencies
The person completing a dependent task may not be the person capable of resolving the dependency.
A developer waiting for client approval cannot necessarily obtain that approval directly. The account manager may be better positioned to coordinate the decision.
For important dependencies, establish who provides the required input, who receives it and who is responsible for following up when it is late.
This makes ownership clear before an issue arises.
5. Maintain a dependency register
A dependency register is a record of important relationships that require ongoing coordination, particularly across teams, suppliers and projects.
It can complement the project schedule by recording information that may not be apparent from dates and task relationships alone.
Here is an example:
| Dependency | Owner | Needed by | Status | Contingency |
|---|---|---|---|---|
| Client design approval | Account manager | Day 6 | At risk | Schedule a live review |
| Approved website content | Content lead | Day 10 | Confirmed | Prioritise essential pages |
| Testing environment | IT lead | Day 10 | Pending | Confirm backup environment |
| Development completion | Technical lead | Day 10 | On track | Review remaining scope |
Larger projects may also require fields for the expected availability date, affected milestones, escalation contact and potential financial impact.
Focus the register on dependencies that require active management. Routine task relationships can remain within the project schedule.
6. Review dependencies before they become blockers
A progress meeting that focuses entirely on completed and overdue tasks offers a limited view of project health.
Instead, examine the activities due to begin during the next one or two weeks.
Are their prerequisites expected to be ready? Have external approvals been confirmed? Are the required specialists still available?
If the answer is uncertain, the project manager has an opportunity to intervene while there is still time to adjust the plan.

What should you do when a project dependency is delayed?
The natural response to a late dependency is to move the affected activity to a later date. Before doing so, examine the alternatives.
| Situation | Possible response |
|---|---|
| A client approval is delayed | Arrange a focused review meeting and agree on a revised decision date |
| A specialist is unavailable | Review alternative resources or adjust the order of independent work |
| A required deliverable is incomplete | Determine whether an approved portion can support downstream activities |
| A dependency affects the critical path | Assess schedule recovery options and revised delivery commitments |
| A supplier delivery is late | Evaluate approved alternatives and update the affected teams |
Consider the website project discussed earlier. If design approval is delayed, final page development may need to wait. However, development environment setup, technical configuration and test preparation could continue if they have no unresolved prerequisites.
The aim is to recover useful working time without creating unnecessary rework.
For client-facing projects, the review should also include commercial consequences. A delayed milestone may affect invoicing dates, subcontractor bookings or the amount of billable capacity available for other projects.
These considerations can change which recovery option makes the most business sense.
Common dependency management mistakes
Assuming every dependency is permanent
Some relationships exist because of temporary resource limitations or established working habits. When those conditions change, the dependency may no longer be necessary.
Creating circular dependencies
A circular dependency occurs when activities rely on each other in a sequence that cannot be completed.
For example, content production requires final design approval, while the design cannot receive final approval until the content is complete.
The team could resolve this by agreeing on preliminary content requirements and an initial design direction before progressing to final production.
Using fixed dates to hide scheduling problems
Assigning a fixed start date to an activity doesn’t make its prerequisites available.
Build the logical relationships first, then assess whether the resulting schedule meets the required deadline.
If it doesn’t, review the scope, resources, sequencing or delivery commitments.
Tracking completion without checking readiness
A task marked complete may still have an outstanding handover, missing attachment or unconfirmed approval.
Define what completion means for important predecessor activities so the receiving team knows when it can safely proceed.
Bring dependency management into everyday project work with Skarya
A dependency map is useful during planning. Its value increases when teams can refer to those relationships while carrying out their day-to-day work.
With Skarya, project managers can review task relationships, schedules, assignments and progress within their project management workspace.
The Dependencies tab provides visibility into related activities and their associated information, helping team members understand what their work relies on.
Timeline views give managers a chronological perspective of scheduled work, making overlapping activities and delivery sequences easier to review. When a dependency changes, this provides context for assessing which dates and assignments may need adjustment.
Resource planning adds another important dimension. A task may be ready to start from a technical perspective, but the person required to complete it may already be committed to another project. Reviewing team capacity alongside project schedules helps managers account for these situations.
Combined with task statuses, milestones and project boards, these capabilities support dependency management throughout delivery, rather than limiting it to the initial planning stage.
If you’re still developing your project plan, explore our guide on how to create a project schedule that holds up in real delivery.
Plan projects around the work, the people and the commitments that connect them.
Explore Skarya’s project management capabilities or book a demo to see how it can support your team’s delivery process.
Frequently asked questions
What is an example of a project dependency?
A website launch depends on completed development, approved content and successful testing. If any required activity is incomplete, the launch may need to be rescheduled.
What is the difference between a dependency and a prerequisite?
A prerequisite is a condition that must be satisfied before an activity can proceed. A dependency describes the relationship between that activity and the work or condition it relies on. Some scheduling dependencies relate to completion rather than the start of an activity.
Can a project have multiple critical paths?
Yes. A project can contain multiple sequences of activities that determine the same earliest completion date. A delay along any critical path can affect the project’s finish date unless corrective action is taken.
How do you identify hidden dependencies?
Review approvals, access requirements, shared resources, external commitments and informal handovers. Discuss upcoming activities with the people responsible for completing them to identify requirements that may be absent from the schedule.
Can project dependencies change during execution?
Yes. Changes to scope, staffing, technical requirements or delivery conditions can introduce new dependencies or remove existing ones. Project managers should update the schedule when these relationships change.